Monday, 13 Oct 2025
  • About us
  • Our policy
  • Blog
  • Contact
Subscribe
thepatriotnewsonline.com
  • Home
  • Politics

    Napo Reinforces NPP’s Global Conservative Ties at UK Party Conference

    By Agyemkum Tuah

    The Kennedy Adjepong’s Factor.

    By Thepatriotnewsgh

    Galamsey financiers are economic terrorists, we must face them boot-for-boot – Prof. Asare

    By Agyemkum Tuah

    Ntim Fordjour Claims Lack of Funds is Behind Speaker Bagbin’s Delay in Reconvening Parliament

    By Agyemkum Tuah

    Gov’t breached Constitution in US deportee agreement – NPP

    By Agyemkum Tuah

    Galamsey: Ghana must act fast to outlaw surface mining – UTAG Vice President warns

    By Agyemkum Tuah
  • Business
  • Opinion

    Ghana Exports Gold To Import Noodles

    By Thepatriotnewsgh

    Ghana Navy Probes Pirate Attack on Fishing Vessel Amid Rising Maritime Security Concerns

    By Thepatriotnewsgh

    Police launch probe into killing of immigration officer at Gbintiri checkpoint

    By Agyemkum Tuah

    Godfred Dame: Ayine’s press conferences marred by falsehoods

    By Thepatriotnewsgh

    Mahama govt scores poorly on energy, environment after 120 Days — IERPP’s Dr. Baafi

    By Thepatriotnewsgh

    Ablakwa To Ghanaians: Criminal Deportees Won’t be allowed entry into Ghana

    By Agyemkum Tuah
  • Health

    Health Alert: 42 H3N2 Cases Confirmed In Greater Accra Region

    By Agyemkum Tuah

    “Show mercy to staff nurse” — Health Minister appeals to Ghana Health Service

    By Agyemkum Tuah

    Ghana Health Service Queries Nurse Over Alleged Insults Directed at Health Minister

    By Agyemkum Tuah

    Mental health crisis deepens in Ghana amid stigma and neglect, psychiatrist warns

    By Agyemkum Tuah

    Indian Police Arrest Owner Of Cough Syrup Company Linked To Deaths Of 17 Children

    By Agyemkum Tuah

    WACCBIP Team at the University of Ghana Wins Prestigious Award in 2025 Vivli AMR Surveillance Data Challenge

    By Agyemkum Tuah
  • Pages
    • About us
    • Our policy
    • Contact US
  • Health
  • Sports
  • World
  • Lifestyle
  • Travel
  • Health
  • Sports
  • World
  • Lifestyle
  • Travel
Font ResizerAa
thepatriotnewsonline.comthepatriotnewsonline.com
  • My Saves
  • My Interests
  • My Feed
  • History
  • Travel
  • Opinion
  • Politics
  • Health
  • Technology
  • World
Search
  • Home
  • Politics
  • Business
  • Sports
  • Opinion
  • Health
  • Travel
  • World
Have an existing account? Sign In
Follow US
© The Patriot News Network. All Rights Reserved.

Home » Built and forgotten: 62 completed Gov’t projects worth GHC52.9 million abandoned

General newsGovernance

Built and forgotten: 62 completed Gov’t projects worth GHC52.9 million abandoned

Thepatriotnewsgh
Last updated: September 8, 2025 8:47 pm
Share
SHARE

Sixty-two government infrastructure projects, completed between 2016 and 2024, are yet to be put to use across the country, raising queries from the Auditor-General.

The state spent about GHC52.9 million on these unused facilities. They include school buildings meant to reduce classroom congestion, health facilities meant to provide lifesaving care, market sheds meant to boost local commerce, police stations/posts meant to provide security, and sanitation projects that could curb disease outbreaks.

These projects were executed in 23 districts across 13 regions, according to the Auditor-General’s 2024 report. The Ashanti Region leads with 12 projects yet to be put to use, followed closely by the Upper East Region with 11 projects.

The report assigned varying reasons for the failure of authorities to make use of the facilities. 

For instance, in the Bono Region, a District Police Headquarters was built at Banda Ahenkro in 2021 but the Ghana Police Service refused to occupy the facility as the service demanded the facility be furnished. The Police Service also requested several additions and changes to the structure.

In the Awutu Senya District of the Central Region, completed market sheds at Bentum and Senya Bereku remain unused since 2023, because the projects were cited far away from the main community.

In other areas, the completed infrastructure projects are not being used for reasons such as the absence of electricity and water supply to the facilities. Disputes over the ownership of lands on which the projects are sited have also stopped the beneficiaries from putting them to use, according to the Auditor-General’s report.

n some instances, however, the Auditor-General says, no cogent reason was provided by the authorities for their refusal or failure to make use of the facilities.

One significant project lying idle is a two-storey structure with 40 lockable stores at Jisonayili in the Sagnarigu District of the Northern Region. Completed in October 2023, it cost the state GHC9,544,020.66. The Auditor-General’s report indicates that no reason was given by the management of the assembly for why the facility remains unused.

A section of the 2-storey building complex at Jisonayili

Still in Jisonayili, another costly project sitting idle is a two-storey complex comprising 72 lockable stores, a police post, a crèche, an abattoir, and market stalls. Completed in October 2023, the state paid GHC8,631,803.83, and yet there seems to be no attempt to make use of it.

At the mechanics’ enclave in the Upper East Region, a retaining wall and filling works were completed in June 2021, costing the taxpayer GHC2,297,863.64. Yet, they remain unused, with no reason given.

The mechanic enclave is located in a waterlogged area around the Bulk Oil Storage Transportation (BOST) depot in the Bolgatanga Municipality. And in order to protect the site from getting flooded, the retaining wall was constructed, and filling works

Another project in the Upper East Region, comprising two mechanic sheds, a police station, and a public washroom, has remained unused since June 2021, with no explanation, according to the Auditor-General’s report. It cost the taxpayer GHC1,999,706.94.

The total cost of these four projects in the Upper East Region alone stands at GHC22.5 million, representing 42.5% of the GHC52.9 million for the larger pool of 62 completed projects lying idle across the country.

There are other projects, which cost less than one million cedis each and are also yet to be put to use. For instance, in the Eastern Region, an office for the National Health Insurance Scheme was constructed in Atiwa. Out of the contract sum of GHC299,297.00, the contractor was paid GHC149,980.50, leaving a balance of GHC149,316.50. The building is yet to be put to use because it has no electricity connection.

Similarly, in the Ketu South District of the Volta Region, a police station was constructed at Gakli in 2024 at a contract sum of GHC480,954.48. Though the contractor received GHC319,287.60 as payment. The facility is yet to be put to use because it has not been connected to electricity.

Disclaimer: The content published on this website is for informational purposes only. The views, opinions, and positions expressed by individual authors or contributors are theirs alone and do not necessarily reflect those of [patriotnewsonline.com]. While every effort is made to ensure accuracy, [patriotnewsonline.com] does not assume any responsibility or liability for any errors, omissions, or outcomes resulting from the use of this information. Readers are advised to verify facts independently and seek professional advice where necessary.

Share this:

  • Click to share on Facebook (Opens in new window) Facebook
  • Click to share on X (Opens in new window) X
Share This Article
Email Copy Link Print
Previous Article Freight Forwarders raise alarm over frequent ICUMS downtimes at Tema Port
Next Article We have names of party bigwigs cutting deals with corrupt officials of previous gov’t – Fifi Kwetey hints
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Your Trusted Source for Accurate and Timely Updates!

Our commitment to accuracy, impartiality, and delivering breaking news as it happens has earned us the trust of a vast audience. Stay ahead with real-time updates on the latest events, trends.
FacebookLike
XFollow
InstagramFollow
LinkedInFollow
MediumFollow
QuoraFollow
- Advertisement -
Ad image

Popular Posts

A Concerned Citizen’s Statement on the Bias of Justice Samuel Bright Acquah

Kwame Baffoe Abronye is not facing justice. He is facing persecution. His only offence is…

By Thepatriotnewsgh

World Cup 2026Q: Black Stars edge closer to qualification with 5-0 win over CAR

The Black Stars are one point from qualification to the 2026 FIFA World Cup following…

By Agyemkum Tuah

Millions of Indigenous People May Lose Voting Rights: Alliance

Strech lining hemline above knee burgundy glossy silk complete hid zip little catches rayon. Tunic…

By Thepatriotnewsgh

You Might Also Like

General newsOpinionPolitics

The Hollow Core of Modern Politics: Ideology, Exploitation, and the Necessity of Thought

By Thepatriotnewsgh
General newsGovernanceNewsPolitics

Bagbin postpones Parliament’s resumption indefinitely

By Agyemkum Tuah
General newsNewsPolitics

September 22, 2025, Declared Public Holiday to Celebrate Kwame Nkrumah’s Founder’s Day

By Agyemkum Tuah
General newsGovernanceNewsPolitics

DStv saga: Sam George lacks “mental rigour” to lead Communication Ministry – Minority

By Agyemkum Tuah
thepatriotnewsonline.com
Facebook Twitter Youtube Rss Medium

About US

ThePatriotnewsonline.com: Your instant connection to breaking stories and live updates. Stay informed with our real-time coverage across politics, tech, entertainment, and more. Your reliable source for 24/7 news.

Top Categories
  • World
  • Opinion
  • Politics
  • Tech
  • Health
  • Travel
Usefull Links
  • Contact Us
  • Advertise with US
  • Complaint
  • Privacy Policy
  • Cookie Policy
  • Submit a Tip

© The Patriot News Network.

All Rights Reserved.

Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?