The New Patriotic Party (NPP) in the Kpando Constituency has called on the Kpando Municipal Assembly to account for GH¢285,369.84 reportedly spent on the construction and landscaping of the Kudzra Roundabout, citing inconsistencies in the Assembly’s budget records.
The party said a review of the Assembly’s financial documents had revealed that the project was recorded as fully completed and paid for in its June 2026 Mid-Year Budget Review, but could not be traced in the corresponding approved or revised budget.
In a statement signed by its Constituency Communications Officer, Dennis Lewis Addeh Statesman, the NPP said the discrepancy raised important questions about the source of funding and the financial arrangements behind the project.
The party pointed to page 23 of the Assembly’s June 2026 Mid-Year Budget Review, under the section on Key Performance Achievements by Government’s Priority for 2025, specifically Infrastructure Delivery and Management.
According to the NPP, the document listed the construction and landscaping of the Kudzra Roundabout as one of the Assembly’s achievements, with a contract sum of GH¢285,369.84, payments made amounting to the same figure and an outstanding balance of GH¢0.00.
The party, however, said concerns had emerged following questions it raised about the expenditure on radio, particularly because the project and its financial details were reportedly missing from the corresponding approved budget.
It stressed that although the physical existence of the roundabout in Kpando was not in dispute, the Assembly needed to explain how the project was financed and why the reported expenditure was not reflected in the approved budget.
Mr Addeh Statesman questioned whether the project was funded through the Assembly’s resources or by an external source, including a private individual, corporate organisation, development partner or non-governmental organisation.
He further demanded an explanation for the Assembly’s decision to record the full contract sum as payment made and present the project as one of its achievements if another entity had financed the construction.
The NPP also raised concerns about whether the Assembly was taking credit for a project funded by an external party or whether GH¢285,369.84 in public funds had actually been spent without the expenditure being captured in the approved budget.
It maintained that the issues raised were legitimate matters of public interest requiring clarification and documentary evidence, rather than allegations of wrongdoing.
The party is therefore demanding that the Assembly disclose the actual source of funding for the roundabout, publish the contract agreement and identify the contractor responsible for the project.
It also wants evidence of the reported GH¢285,369.84 payment, an explanation for the project’s appearance in the June 2026 Mid-Year Budget Review despite its absence from the approved budget, and clarification on whether the construction was financed with public funds or private support.
The NPP insisted that residents of Kpando were entitled to know how public resources were utilised, arguing that all government expenditure must be properly documented, transparently reported and subjected to public scrutiny.
It added that while development projects could be celebrated as achievements, such recognition must be accompanied by clear financial accountability.
The Kpando Municipal Assembly had not responded to the concerns raised by the NPP as of the time of filing this report.